Nuclear plant deal delayed as Westinghouse executives are detained

Following the detention of two Westinghouse managers on 4 November in an investigation concerning Ostrołęka, the signing of advance payment agreements worth about PLN 1 billion for components of Poland’s first nuclear power plant has been delayed. Negotiations on the EPC contract are still ongoing.

Detentions and charges

The detentions on 4 November related to an investigation into irregularities in the construction of a coal-fired unit at the Ostrołęka Power Plant. Among the 25 people detained were Mirosław K., president of Westinghouse’s Polish branch, and Robert N., who took part in negotiations on the nuclear power plant contract. They were charged with failure to perform duties and causing major property damage, and then released with preventive measures that included a property bond. The damage across the entire investigation is estimated at over PLN 1 billion. The detained individuals have not been convicted, and the case is at the preparatory proceedings stage.

Westinghouse stated that the investigation concerns a project carried out for the detainees’ former employer and has no connection with its activities in Poland or with the EPC contract negotiations.

Advance payments for long-lead items

According to reports, Polskie Elektrownie Jądrowe (PEJ) was to sign advance payment agreements with its US partner for so-called Long Lead Items, meaning components whose production and delivery require years of lead time. The amount is around PLN 1 billion. The detentions coincided with a moment when signing these agreements was planned in Warsaw, and the signing was postponed. Sources do not indicate that Westinghouse formally halted payments; the reported issue is a suspension of the contract signing.

In mid-November, PEJ and the Westinghouse-Bechtel consortium signed a letter of intent on ordering key components, in order to reduce the risk to the schedule. The reactor vessel is to arrive from Japan, and the nuclear island is to be built in the USA.

Costs and EPC negotiations

PEJ’s cooperation with the consortium currently rests on a bridging agreement (EDA) from April 2025. Former PEJ employees claim the company covers the partner’s operating costs based on monthly invoices. Energy Minister Miłosz Motyka responded to these reports at the P-TEC conference. He stressed the partnership nature of the cooperation and assured that the EPC contract is to include mechanisms protecting the interests of taxpayers.

PEJ announced that in September it agreed with the consortium on the main commercial terms of the EPC contract. The goal is to close negotiations by the end of 2026, and according to PEJ President Marek Woszczyk, the signing itself will take place in 2027. The amounts in negotiations over a higher budget for the entire investment have not been disclosed.

On Wednesday, 18 November, the Ministry of Energy reminded on X that construction is to start in 2028, and the first unit is to begin operating in 2036.

Earlier, we wrote about the signing of the bridging agreement for the construction of the power plant.