Section speed cameras on A2 to roll out in stages, covering 48 km of motorway

On the A2 motorway between Warsaw and Łódź, which is being expanded, section speed checks are set to begin within the next two weeks. The longest of them, which will cover 48 km, will be a national record, and the limit across the entire construction site is 70 km/h.

Launch dates: two stages

According to the Centre for Automatic Road Traffic Supervision (CANARD), the systems will be switched on in stages: the first between 30 November and 4 December, the second in the first half of December. Exact days have not been given.

Where the cameras will be

Two stretches of the route, in both carriageways, will be under supervision:

  • Koszajec – Michałówek – 48 km, from just past Pruszków to the point before the Łowicz and Skierniewice exit; once launched, this will be the longest section check in Poland,
  • Dzierzgów – Niesułków – about 30 km, from the Stryków interchange to the Łowicz and Skierniewice exit.

Section measurement does not check speed at a single point. The system records the time a vehicle enters and leaves the section and calculates the average speed from that. Simply slowing down before the gantry is not enough – the average over the full 48 km must not exceed the limit. At 70 km/h, travelling this section takes just over 41 minutes, not counting traffic jams.

70 km/h limit across the whole construction section

The 70 km/h limit applies to the sections of the A2 being upgraded from 20 November. The GDDKiA responded on X to drivers who questioned its justification. The directorate explains that the entire section covered by the expansion is formally a construction site, which is why the limit also applies where no work is currently taking place.

What happens after construction ends

The GDDKiA plans to keep two lanes in each direction during construction; the works are due to last until April 2028. According to current announcements, the directorate does not plan to leave the measurements on the A2 after the investment is completed.

Beware of fake SMS messages

The Road Transport Inspection (ITD) warns of fraud attempts. Messages about alleged violations on the A2, with a payment link, are being sent to random phone numbers. Inspectors do not send SMS messages – correspondence about offences arrives by post.

Dorota Lune

Dorota Lune, redaktorka serwisu DigitalNexus.pl. Zajmuje się tematyką show-biznesową, bieżącymi informacjami jak i ciekawostkami ze świata. Ukończyła dziennikarstwo na UPJPII w Krakowie. Wcześniej pracowała w branży turystycznej. W wolnych chwilach lubi podróżować i czytać książki.